Cutting a chemical plant’s valve-driven shutdown exposure from 6 weeks to 9 days
Order-to-delivery lead time
41 days23 days
over a 150-day programme
A specialty chemical producer in Antwerp could not accept six-week lead times on API 6D trunnion ball valves for a scheduled turnaround, because each week of delay extended the plant outage.
Wenzhou Yongtai Valve Manufacturing Co., Ltd.Read the evidence →